1 Excavation of area to approximate depth of 100mm.
2 This is a good time to install a treated timber/plastic leisure edging frame if required.
3 Dispose of excavation waste via means of skips etc.
4 Import MOT- type 1 crushed stone approximate depth of 50mm.
5 Compact with compactor plate.
6 Insert Leisure geotextile membrane fabric, weed and aggregate loss control.
7 Import 6mm down crushed sharp sand (zone 111) approximate depth of 45mm.
8 Compact with compactor plate.
9 Screed out sand ready for laying of artificial grass.
10 Roll out artificial grass.
11 Tape and glue all joints if required and cut to size.
12 Secure the grass down around the edges using galvanised stakes.
13 Sand fill the carpet with 30s brown quarts sand/rubber granules if required. (Optional)
14 Brush up the pile with a stiff bristled brush or power brush.